I know this may seem overwhelming, but please look through this list! This is a list of UPCOMING PIPELINES that have yet to be fought. If there is one coming to your area please team up and unite with organizations, groups and water protectors to start peacefully fighting the use of of dirty fuel. If you are already fighting one of these pipelines please contact us and we will add it to our Pipelines page. This is by no means a list of every single pipeline being built right now, this is just the beginning. All info is subject to change at any time on this list so please research before you organize!
Oil Pipelines
BAKKENLINK PIPELINE
Project: Dry Creek to Beaver Lodge Project
Type: Project includes the construction of 16-inch welded steel crude oil pipeline
Miles: 37
Location: Johnson’s Corner, ND - Tioga, ND
Start: 2017
Completion: 2018
BOE PIPELINE LLC
Project: Bakken Oil Express II Pipeline
Type: Project involves construction of 16-inch pipeline
Miles: 42
Location: Dunn County, ND and McKenzie County, ND
Start: 2017
Comments: Pipeline will carry 165,000 bpd of oil, while linking up with the existing 38-mile BOE Pipeline
ENTERPRISE PRODUCTS PARTNERS LP
Project: ECHO, Phase 2
Type: Project includes the construction of 30-inch pipeline
Miles: 17
Location: Baytown, TX
Start: 2017
Completion: 2018
ENTERPRISE PRODUCTS PARTNERS LP
Project: Midland-to-Sealy Pipeline
Type: Project includes the construction of 24-inch pipeline
Miles: 416
Location: Midland, TX - Sealy, TX
Start: 2017
Completion: 2018
HARVEST PIPELINE CO.
Project: Point Comfort Pipeline
Type: Project includes the construction of 36-inch pipeline
Miles: 27
Location: Jackson County, TX - Calhoun County, TX
Start: 2017
Completion: 2018
Comments: Pipeline will integrate with nine major pipelines ( five interstate and four intrastate) and will have a 5 Bcf/d of pipeline takeaway
MAGELLAN MIDSTREAM PARTNERS LP
Project: Howard Lateral
Type: Project includes the construction of bi-directional pipeline and the expansion of the Wolfcamp Connector mainline system
Miles: 49
Location: Howard County, TX - Glasscock County, TX
Start: 2017
MINNESOTA PIPE LINE CO. LLC
Project: Minnesota PipeLine Reliability Project
Type: Project includes adding six pump stations to MPL Line 4 and upgrading existing stations
Location: Howard County, TX - Glasscock County, TX
Start: 2017
Completion: 2018
Comments: Project will allow the pipeline to operate at its original design capacity of 350,000 bpd of crude oil
Gas Pipelines
Enbridge
Project: Atlantic Bridge
Type: Expansion and new pipeline
Location: New York, Massachusetts, Connecticut, Maine
Start: FERC approval in Jan 2017
Completion: November 2017
Comments: The project calls for an expansion of the Algonquin Gas Transmission and Maritimes & Northeast Pipeline systems, including about 6.3 miles of new pipeline construction and a new compressor station in Massachusetts
Transco
Project: Diamond East
Type: Expansion
Location: Lycoming, PA to Mercer, NJ
Miles: 50
Start: 2017
Completion: 2018
Gulf South Pipeline Company
Project: Costal Bend Header Project
Location: Brazoria and Wharton Counties. Texas and New Wilson Compressor Station in Wharton County, Texas
Miles: 66 of pipeline
Start: Spring 2017
Comments: The Project will also include expansion of a portion of Gulf South’s mainline system and a new interconnect to supply the Coastal Bend Header consisting of:
- New North Houston Compressor Station - Approximately 10,700 HP located in Harris County, Texas
- New Brazos Compressor Station – Approximately 26,400 HP located in Fort Bend County, Texas
- Existing Magasco Compressor Station – Approximately 15,748 HP located in Sabine County, Texas
- Piping modifications to the existing Goodrich Compressor Station located in Polk County, Texas
Columbia Pipeline Group
Project: Columbia Gulf Transmission / Cameron Access Project
Type: 36-inch diameter natural gas pipeline
Location: Jefferson Davis, Cameron, and Calcasieu Parishes, Louisiana
Miles: 34
Start: Gulf proposes an in-service date of December, 2017, Being built NOW
Comments: Directionally drilled beneath the Gulf Intracoastal Waterway (GIWW) and the Calcasieu Ship Channel
Columbia Pipeline Group
Project: WB XPress Project
Location: Fairfax County, Shenandoah County, Virginia - Randolph and Pendleton Counties, Braxton County, Upshur County, Randolph County, Hardy County. West Virginia
Miles: 28
Start: winter of 2017
Comments: This project involves new pipeline, modifications of existing pipeline and modifications of several compressor stations along with new compressor stations
Columbia Pipeline Group
Project: Central Virginia Connector
Location: Louisa and Goochland Counties, Virginia
Start: Columbia proposes to begin construction with tree clearing starting in the Fall/Winter of 2017, and pipeline replacement/installation starting Spring 2018
Enbridge
Owner: Texas Eastern Transmission, LP
Project: Access South Project
Location: Pennsylvania, West Virginia, Ohio, Kentucky, Tennessee, Alabama & Mississippi
Completion: November 2017
Magnum Gas Header Pipeline/ Storage Project
Project: Gas storage facility along with pipeline construction
Location: Millard County, Utah
Miles: 61
Start: Projected construction for winter 2017
Comments: Involves the construction of underground storage caverns in the only gulf-style salt dome in the Rocky Mountain Region.
Project: Driftwood LNG Pipeline
Type: Project involves dual lay of 42-inch, single lay of 42-inch and single lay of 36-inch pipeline
Miles: 96
Location: Calcasieu Parish, LA - Evangeline Parish, LA
Start: 2017/2018
WILLIAMS PARTNERS LP
Project: Gulf Connector Expansion Project
Location: Texas - Louisiana
Start: 2017
Completion: 2019
Comments: Project will deliver natural gas to feed two liqued natural gas export terminals in Texas and has led with the FERC
Project: IPL Pipeline
Type: Project includes the construction of 16-inch pipeline
Miles: 12.3
Location: Scott and Clinton counties, IA
Start: 2017
Comments: Project is currently awaiting approval from the Iowa Utilities Board
AMERICAN MIDSTREAM PARTNERS LP
Project: Magnolia Intrastate Extension
Type: Project includes the extension of the Magnolia Intrastate Pipeline
Miles: 45
Location: Alabama
Start: 2017
Completion: 2019
Project: Mountaineer XPress Project
Type: Project includes the construction and operation of various diameter pipeline, three new compressor stations and modifcations to three existing compressor stations and one regulating station
Miles: 165
Location: Marshall and Cabell counties, WV
Start: 2017
Completion: 2018
EAGLE LNG PARTNERS
Project: Jacksonville Project
Type: Project includes the construction of a storage facility that will receive natural gas transported by a local utility through existing and expanded pipelines located adjacent to the Jacksonville project site
Location: Louden County, VA - Franklin County, PA
Comments: Upon FERC review of all 13 Resource Reports, and Eagle LNG addressing any concerns identified by FERC, Eagle LNG anticipates that FERC will grant Filing status in 2017
EASTERN SHORE NATURAL GAS
Project: 2017 Expansion Project
Type: Project includes pipeline looping, upgrades to existing metering facilities and installation of an ad-ditional 3,550 horsepower compressor unit at the existing Daleville Compressor Station
Miles: 33
Location: Pennsylvania, Maryland, Delaware
EQT MIDSTREAM PARTNERS LP
Project: Equitrans Expansion Project
Type: Project includes the construction of 6-inch to 30-inch pipeline and expansion of existing compressor stations
Miles: 8
Location: Greene, Allegheny and Washington counties, PA; Wetzel County, WV
Start: 2017
Completion: 2017
GULF SOUTH PIPELINE LP
Project: St. Charles Parish Expansion Project
Type: Project includes the construction of 900 feet of 16-inch pipeline and a compressor station
Location: Montz, LA
Start: 2017
MILLENNIUM PIPELINE CO.
Project: Eastern System Upgrade
Type: Project includes the construction of 7.8 miles of 36-inch looped pipeline, upgrades to the existing Hancock Compressor Station, new compression capabilities and upgrades to existing Ramapo Meter and Regulation Station
Miles: 10
Location: Rockland County, NY
Start: 2017
Completion: 2018
Comments: The project will be co-located along Millennium’s existing 244 miles of right- of-way
MILLENNIUM PIPELINE CO.
Project: Valley Lateral Project
Type: Project includes the installation of a 16-inch lateral
Miles: 7.8
Location: Orange County, NY
Start: 2017
NATIONAL FUEL GAS SUPPLY CORP.
Project: West to East – Overbeck to Leidy Project
Type: Project includes the construction of 24-inch pipeline and compressor stations
Miles: 82
Location: Weedville, PA - Renovo, PA
Start: 2017
Completion: 2018
Comments: Project will consist of two sections: The East Section will begin near Weedville, PA and end at Leidy Station near Renovo, PA; and the West Section will begin at Overbeck Station near Sigel, PA and end near Weedville, PA
Project: Oregon Pipeline
Type: Project includes the construction of 36-inch pipeline
Miles: 85
Location: Warrenton, OR – Woodland, WA
Start: 2017
SPECTRA ENERGY
Project: Greater Philadelphia Expansion Project
Type: Project includes the replacement of existing pipeline with a larger diameter pipe and adding new pipeline looping
Miles: 35
Location: Philadelphia, PA
Completion: 2019
TALLGRASS ENERGY
Project: Prairie State Pipeline
Type: Project includes the construction of of large diameter pipeline running in a generally north-south orientation
Miles: 140
Location: Douglas County, IL - Chicago Market Centre
Start: 2017
Completion: 2019
TRANSCAMERON PIPELINE LLC
Project: TransCameron Pipeline
Type: Project includes the construction of of 42-inch pipeline
Miles: 42
Location: Grand Chenier, LA and Johnson’s Bayou, LA
Start: 2017
Completion: 2019
WGL MIDSTREAM INC.
Project: Central Penn Line
Type: Project includes the construction of a new 42-inch, 1480 psi gas transmission pipeline
Miles: 177
Location: Susquehanna County, PA - Lancaster County, PA
Start: 2017
Completion: 2018
WILLIAMS PARTNERS LP
Project: Northeast Supply Enhancement
Type: Project includes the construction of 26-inch and 42-inch pipeline
Miles: 35
Location: New York Bay; Lancaster County, PA; Middlesex County, NJ
Start: 2017
Comments: Project is part of an expansion of the Transco interstate natural gas pipeline
WILLIAMS NORTHWEST PIPELINE
Project: Washington Expansion Project
Type: Project includes the construction of ten segments of 36-inch pipeline loop in the existing right-of-way and compression stations
Miles: 140
Location: Whatcom County, WA - Woodland, WA
Start: 2017
Completion: 2018
COLUMBIA PIPELINE GROUP
Project: B-System Project
Type: Project includes the construction of new pipeline and the replacement of a 13.8- mile, 20-inch pipeline - the B111 Line - and the replacement of a 7-mile, 20-inch pipeline - the K270 Line. Project also includes upgrades to ancillary B-System equipment and facilities.
Miles: 20.8
Location: Fairfield and Franklin counties OH
Start: 2017
Completion: 2018
Comments: Project is part of Columbia’s ongoing Modernization Program, filed by Columbia on February 7, 2017
COLUMBIA PIPELINE GROUP
Project: Leach XPress
Type: Project includes the construction of 30-inch and 36-inch natural gas pipeline and compression facilities
Miles: 160
Location: Marshall County,Wayne County, WV - Pennsylvania - Ohio
Start: Approved in January 2017
COLUMBIA PIPELINE GROUP
Project: Gulf XPress (GXP)
Type: Project includes the construction of 24-inch, 36-inch and 42-inch pipeline
Miles: 7
Location: Ceredo, WV
Start: 2017
WISCONSIN GAS
Project: Dovre Lateral Natural Gas Pipeline
Type: Project includes the construction of new 12-inch steel mainline
Miles: 9.5
Location: Barron County, WI
Start: 2017
Completion: 2018
WISCONSIN GAS
Project: Wilson Lateral Natural Gas Pipeline
Type: Project includes the construction of new 12-inch steel mainline
Miles: 8.2
Location: Barron County, WI
Start: 2017
Completion: 2018
Canada Gas pipelines
NOVA GAS TRANSMISSION LTD.
Project: 2018 NGTL Expansion
Type: Project includes the construction of 20-inch to 48-inch pipeline, one new compressor, 35 new and expanded meter stations and other associated facilities
Miles: 55
Location: Alberta and British Columbia
Start: 2017
Completion: 2018
Comments: Canadian government approved the project with 36 conditions attached
NOVA GAS TRANSMISSION LTD. TransCanada
Project: North Montney Mainline Project
Type: Project includes the construction of 42-inch pipeline and include associated metering facilities, valve sites, and compression facilities
Miles: 190
Location: Peace River, AB
Start: 2017
Completion: 2019
Comments: Project is in the process of satisfying the various pre-construction conditions
PEMBINA PIPELINE CORP.
Project: NEBC Expansion
Type: Project includes the construction of 12-inch pipeline with a base capacity of up to 75,000 bpd that will parallel the company’s Blueberry Pipeline
Miles: 99
Location: Taylor, BC - Clair Creek, BC
Start: 2017
SPECTRA ENERGY CORP.
Project: Westcoast Connector Gas Transmission
Type: Project includes the construction of two 48-inch pipelines
Miles: 528
Location: Cypress, B.C. - Prince Rupert, B.C.
Completion: 2020
Coastal GasLink Pipeline
Type: Project includes the construction and operation of new pipeline
Miles: 416
Location: Dawson Creek - Kitimat, B.C.
Start: 2017
Completion: 2019
Other Products Pipelines (neither oil or gas)
BUCKEYE PARTNERS LP
Project: Michigan/Ohio Pipeline Expansion Project (Phase II)
Type: Project includes the reversal on a portion of the existing Laurel Pipeline to facilitate the transportation of re ned petroleum products
Location: Pittsburg, PA
Completion: 2018
DOS ÁGUILAS PIPELINE LLC
Owner: Howard Energy Partners LLC
Project: Dos Aguilas Project
Type: Project includes the construction of four 12-inch pipelines – Border Express Pipeline (Corpus Christi, TX – Laredo, TX), Borrego Pipeline (Laredo, TX - International Border Crossing), Poliducto Frontera Pipeline (International Border Crossing - Nuevo Laredo, Tamaulipas) and Poliducto del Norte Pipeline (Nuevo Laredo, Tamaulipas - Monterrey, Nuevo Leon) – and four new re ned liquids terminals
Miles: 287 (141 miles in the U.S. and 146 miles in Mexico)
Location: Corpus Christi, TX - Monterrey, Nuevo Leon
Start: 2017
Completion: 2018
ENTERPRISE PRODUCTS PARTNERS
Project: Lou-Tex Pipeline Conversion
Type: Project includes converting the 263-mile long, bi-directional pipeline chemical grade propylene service to PGP service
Location: Sorrento, LA - Mont Belvieu, TX
Start: 2017
Completion: 2020
KINDER MORGAN INC.
Project: UTOPIA Project
Type: Project includes the construction and operation of 12-inch pipeline
Miles: 240
Location: Harrison County, OH - Riga, MI - Windsor, Ontario
Start: 2017
Completion: 2018
Mexico pipelines
MONTERRA ENERGY
Project: Monterra del Centro Pipeline
Type: Project includes the construction of 18-inch pipeline along existing right-of- way
Miles: 167
Location: Tuxpan, Veracruz - Tula, Hidalgo
Start: 2017
Completion: 2018